BU 396 Unit 6 risk register example

Managing Project Risks Herzing University Free custom sample in 24 to 48h

This BU 396 Unit 6 risk register assembles a composite riverfront festival's risk work into one maintained document as of July 15, with active entries, closed entries, a realized risk that became an issue and the change log that proves the register is kept current. Herzing BU 396 asks for a maintained register rather than a produced one, and the sample gives project management students a wide table with permanent identifiers, dates raised and reviewed, category, current and remaining ratings, dated actions, owners, triggers and status. Closed entries stay visible, including a permit risk closed on approval and a tourism grant opportunity realized. A sponsor withdrawal is shown moving from the register to the issue log and back to resolution. The change log records nine dated changes, and a reading section interprets the register's state five weeks before the event.

CourseBU 396 Managing Project Risks
UnitUnit 6
Paper typeRisk register
LengthAbout 520 words, 4 pages
FormatAPA 7 student paper
SchoolHerzing University
ProgramBS in Project Management
UpdatedSeptember 2026

Free sample paper for BU 396 Unit 6

1

The Riverfest Risk Register as of July 15: Seventeen Entries, Three Closed, One That Became an Issue, and the Change Log That Proves It Is Maintained

Student Name

Business, Herzing University

BU 396: Managing Project Risks

Instructor Name

July 15, 2026

What this page is doingThe title gives the register's date and status counts and points to the change log. A register that shows closed entries, a realized risk and its revision history reads as a working document rather than a one-time list.
2

The Riverfest Risk Register as of July 15: Seventeen Entries, Three Closed, One That Became an Issue, and the Change Log That Proves It Is Maintained

About This Register

This is the maintained risk register for the fictional Riverfest as it stood on July 15, 2026, five weeks before the festival. It assembles the work of earlier units: the identifiers and statements from the identification workshop, the ratings from the qualitative scoring, the exposure estimates from the quantitative analysis and the responses chosen in Unit 5. Each entry holds a permanent identifier that is never reused, the date it was raised and last reviewed, its category, a short form of its statement, its current and remaining ratings, the chosen response, actions with owners and dates, the trigger being watched and a status. Guidance from the Project Management Institute (2019) describes the register as the living record of a project's risks, and it becomes living only when its status and history change as the project moves.

Active Entries

The table shows the active entries. Ratings are shown as probability by impact, with the score in parentheses; remaining ratings describe the position once responses are complete.

IDRaised / reviewedCategoryEntryCurrentRemainingResponse and actionsOwnerTriggerStatus
R01Feb 2 / Jul 14WeatherStorms force park closure3x5 (15)3x2 (6)Transfer and mitigate: insurance bound Apr 20; monitoring service contracted May 1; shelter plan drilled Jul 30Events directorSevere thunderstorm watch for the county within 48 hoursActive
R03Feb 2 / Jul 14WeatherHeat illness overloads first aid3x4 (12)2x3 (6)Mitigate: two cooling tents, free water stations, added EMS crew; ordered by Aug 1Operations leadHeat index forecast above 100 degreesActive
R02Feb 2 / Jul 1WeatherWind damages structures2x5 (10)1x5 (5)Mitigate: engineered tents, wind-speed shutdown rule of 35 mphProduction managerSustained wind forecast above 25 mphActive
R07Feb 2 / Jul 14PeopleToo few volunteers3x3 (9)2x3 (6)Mitigate: shift incentives, partner with two civic clubs by Jul 25Volunteer coordinatorSign-ups below 80% of target on Aug 1Active
R14Feb 2 / Jul 14FinanceSlow advance ticket sales2x3 (6)2x2 (4)Mitigate: July promotion with radio partnerFinance managerWeekly sales below plan two weeks runningActive, rerated down
R11Feb 2 / Jun 30SafetyCrowd disorder at headliner2x4 (8)1x4 (4)Mitigate: police staffing plan, barrier layout approvedPolice liaisonIntelligence of planned disruptionActive
R08Feb 2 / Jul 1PeopleHeadliner cancels2x4 (8)2x2 (4)Transfer: replacement clause signed Mar 30Events directorAny notice from agencyActive
R10Feb 2 / Jul 1VendorsFood safety failure2x4 (8)1x4 (4)Mitigate: county inspection before gates open, handwashing stationsVendor coordinatorFailed pre-opening inspectionActive
R09Feb 2 / Jul 14VendorsMore than five vendor cancellations3x2 (6)2x2 (4)Mitigate: deposits collected; waiting list of 10Vendor coordinatorThree cancellations in one weekActive
R12Feb 2 / Jun 15SafetyGenerator failure2x3 (6)1x3 (3)Mitigate: standby main-stage generator bookedProduction managerFailed load test on Aug 21Active
R04Feb 2 / Jul 14WeatherRiver stage closes part of site1x4 (4)1x4 (4)Accept; watch river forecastsOperations leadForecast crest above minor flood stageActive
O1Feb 12 / Jul 1FinanceA sponsor upgrades its tier3x3 (9)Enhance: offer stage naming rightsBoard chairSponsor meeting scheduledActive opportunity
R15Jun 3 / Jul 14PermitsNeighbor complaints about noise3x2 (6)2x2 (4)Mitigate: sound limit and neighborhood letterEvents directorComplaints to cityActive, new entry
What this page is doingEach entry carries dates raised and reviewed, current and remaining ratings, dated actions, an owner, a trigger and a status. Triggers are what turn a register into an early warning system, and many student registers omit them.
3

Closed and Realized Entries

Closed entries stay in the register so the history of the project's risks remains visible. R05, permit approval delayed, was closed on May 13, the day after the city council approved the special event permit. R06, road closure plan changes, was closed on June 10, when the city issued the final plan with no change to the site layout. O2, a state tourism grant, was closed on June 1 when the grant was awarded, a realized opportunity worth $12,000, the kind of upside Hillson (2002) argued registers should track alongside threats.

R13, a verbal sponsor withdraws, occurred. On April 22, one of the three verbal sponsors, representing $18,000, withdrew after a change in its own budget. The register entry was closed as realized, and issue I-04 was opened in the issue log, owned by the board chair. The issue was resolved on May 20, when a backup sponsor from the waiting list signed at $12,000; the remaining $6,000 gap was covered by the realized tourism grant. The other two verbal sponsors had signed agreements by April 1, as the response required.

Change Log

The change log records every change to an entry, which is what marks the register as maintained rather than merely produced.

DateEntryChangeBy
Mar 30R08Replacement clause signed; remaining rating set at 2x2Events director
Apr 1R13Two sponsors signed; one still verbalBoard chair
Apr 20R01Insurance bound; remaining rating 3x2Events director
Apr 22R13Closed as realized; issue I-04 openedEvents director
May 13R05Closed; permit approvedOperations lead
Jun 1O2Closed; grant awardedFinance manager
Jun 3R15New entry raised after neighborhood meetingEvents director
Jun 10R06Closed; road plan finalOperations lead
Jul 14R14Probability lowered from 3 to 2; sales at 104% of planFinance manager

Reading the Register

Three things stand out on July 15. First, the risk profile has improved: two entries have closed, the realized sponsor risk was absorbed within the contingency plan, and ticket sales are ahead of plan. Second, the entries that remain most serious are weather entries whose triggers can only fire in the final days, which is why the review cadence moves to daily in the festival week. Third, a new entry, R15, appeared after identification closed, which bears out the advice from Kendrick (2015) that registers must stay open to new risks as a project reveals them. The register will be reviewed next on July 22. The Cedar Bend Riverfest, its entries and dates are composites created for this course.

References

Hillson, D. (2002). Extending the risk process to manage opportunities. International Journal of Project Management, 20(3), 235-240. https://doi.org/10.1016/S0263-7863(01)00074-6

Kendrick, T. (2015). Identifying and managing project risk: Essential tools for failure-proofing your project (3rd ed.). AMACOM.

Project Management Institute. (2019). The standard for risk management in portfolios, programs, and projects. Project Management Institute.

BU 396 Unit 6 instructions, in plain terms

For Unit 6, students assemble the term's risk work into a complete risk register. Most versions want each entry to carry an identifier, the date raised and last reviewed, its category, a structured risk statement, current and residual ratings, the chosen response, actions with owners and dates, a trigger and a status. Many rubrics ask that closed entries remain in the register and that realized risks be linked to an issue log. A change log is often required to show maintenance over time. Instructors grade the register as a working document rather than a static list, so dates and status changes matter. Expect a wide table plus a change log and a short interpretation, citing risk standards in APA 7, and date the register so the reader knows which moment it captures.

How this BU 396 Unit 6 example is built

The sample explains what each column holds and why a register becomes useful only when it changes. The active entries table lists thirteen entries, each with ratings, dated actions, an owner, a trigger and a status, including one new entry and one rerated down. A section on closed and realized entries explains why three entries closed and how a sponsor withdrawal was handled through the issue log until a replacement was signed. A change log table lists every change with a date and the person who made it. The final section reads the register, noting the improved risk profile, the weather entries still ahead and the lesson from the new entry.

BU 396 Unit 6 rubric: what full points look like

The rubric for the register typically assesses completeness of fields, evidence of maintenance, handling of closed and realized risks and interpretation. Completeness earns full points when every entry carries all the required fields, including triggers and owners. Maintenance is judged by review dates, a change log and status changes over time, as the sample shows. Handling of closed and realized risks rewards registers that keep closed entries and link realized risks to issues. Interpretation scores highest when the paper explains what the register shows about the project's risk position at that date. Instructors also credit new entries added after identification, since they show the register is truly open. A readable table and citations complete the grade.

BU 396 Unit 6 help before you submit

The most common Unit 6 mistake is submitting a register with no dates, which makes it impossible to tell whether it has been maintained. Another is deleting closed risks, which erases the project's history. Students often leave triggers blank, turning the register into a list rather than an early warning system. Some registers assign owners to teams instead of people. Others show no change log, so every entry looks as if it was written the same day. Finally, include at least one entry whose status has changed; a register in which nothing ever closes, opens or moves suggests it was produced once and never used by the team.

Get a BU 396 Unit 6 example written to your instructions

Send the Unit 6 instructions and the rubric in your BU 396 classroom, along with the register format your section specifies if it fixes one. We write a custom example with permanent identifiers, both dates, statements carried forward whole, paired ratings, a written status field and a change log underneath. First custom sample free, back in 24 to 48 hours.

More BU 396 papers and project management samples

BU 396 Unit 6 questions, answered

How many entries belong in the register?

Whatever survived identification and cleaning, which is normally more than the shortlist you modeled and fewer than the raw capture. Where the instructions fix a count, keep the register at that size and note what was excluded and on what grounds. A register holding every idea from the session is unusable, and one holding four entries has not covered the project.

Should closed entries stay in the document?

Yes, marked closed with the date and a line on how it ended. A register showing only live entries hides the work already done and makes the change log unreadable. Closure is also evidence a marker can grade, since an entry closed because its condition expired reads very differently from one closed because the response worked, and the row should say which.

Does the register need a separate issue log?

That depends on the section, since some ask for both and others keep everything in one place. Where both exist, an entry that materializes moves across with its identifier intact and the register records the date and the destination. What causes trouble is leaving a materialized entry open with a probability still attached, because it is no longer uncertain and the rating means nothing.

Where can I find a free BU 396 Unit 6 sample paper?

Everything in the BU 396 Unit 6 register, active and closed entries plus the change log, is open above to read for free. To get a register assembled from your own earlier units, share them with the prompt, and a free custom register will be built for you, usually within two days.

Should closed entries stay in the BU 396 Unit 6 register?

Yes. The sample keeps closed and realized entries with their dates and reasons, because they show the project's risk history and how responses worked. Deleting them makes the register look cleaner but removes evidence that instructors look for.