BU 442 Unit 7 variance analysis with response example

Cost and Time Management Herzing University Free custom sample in 24 to 48h

This BU 442 Unit 7 sample paper tests the variances from a composite Fort Wayne shared kitchen's day 80 earned value against thresholds and turns the ones that matter into actions. Herzing BU 442, Cost and Time Management, requires project management students to end variance work where a reader can act. Four thresholds are applied, including tests for favorable variances and for float consumed. Three cost gaps pass and are traced to physical causes: asbestos in floor mastic, an old footing under the grease interceptor and a utility's relocated service entrance. Only the plumbing delay moves the finish date. Each gap receives an action, an owner and a date, and a recovery plan returns the finish to day 135.

CourseBU 442 Cost and Time Management
UnitUnit 7
Paper typeVariance analysis with response
LengthAbout 800 words, 5 pages
FormatAPA 7 student paper
SchoolHerzing University
ProgramBS in Project Management
UpdatedSeptember 2026

Free sample paper for BU 442 Unit 7

1

Three Gaps Pass the Threshold, One Moves the Finish Date: A Variance Analysis With Response for a Composite Fort Wayne Shared Kitchen at Day 80

Student Name

Business, Herzing University

BU 442: Cost and Time Management

Instructor Name

June 3, 2026

What this page is doingThe title separates gaps that cross a threshold from the one that actually changes the finish, which is the judgment this unit tests. The reader expects triage, not a list of every variance.
2

Three Gaps Pass the Threshold, One Moves the Finish Date: A Variance Analysis With Response for a Composite Fort Wayne Shared Kitchen at Day 80

From Numbers to Decisions

Last week's earned value calculation for the Food Works kitchen project, a composite case built for this course, found a cost variance of -$25,811 and a schedule variance of -$144,700 at day 80. Those totals are made of package-level gaps of very different importance. This analysis tests each gap against thresholds set when the baseline was approved, traces the gaps that pass to a cause in the work rather than in the arithmetic, and attaches a corrective action with a named owner. Fleming and Koppelman (2010) describe thresholds as the device that keeps earned value from burying managers in variances, by directing attention to the few that exceed agreed limits.

The Thresholds

Four thresholds were written into the baseline in March. A cost variance is investigated when it is worse than -5 percent of the package's earned value and larger than $5,000; both conditions must hold, so that small packages do not trigger reviews over trivial sums. A favorable cost variance larger than 10 percent and $5,000 is also investigated, since an underrun can mean work was skipped or credited too early. A schedule gap on a critical path package is investigated if the package is more than two working days late. A schedule gap on a package with float is investigated when it uses more than half of the package's remaining float.

PackageCost variancePercent of earned valueSchedule positionCrosses a threshold?
1.1 Design-$3,500-5.1%CompleteNo: under $5,000
2.1 Demolition and abatement-$5,800-13.8%CompleteYes: cost
3.1 Electrical-$12,200-17.2%About 10 days behind, 35 days of floatYes: cost; schedule within limit
3.2 Plumbing-$8,500-8.9%Finished 6 days late on the critical pathYes: cost and schedule
3.3 Mechanical+$4,000+3.0%CompleteNo: below 10%
4.1 Hood fabrication$00%About 9 days behind, 45 days of floatNo: uses under half of float
5.1 Interior+$1,500+8.1%Started 6 days late, criticalYes: schedule, caused by plumbing
7.0 Project management-$1,311-2.3%Level of effortNo
What this page is doingEach gap is tested against written thresholds, including favorable ones and float-based schedule tests. The design variance is shown failing only the dollar test, which proves the rule was applied rather than assumed.
3

Tracing Causes in the Work

Demolition overran by $5,800 because the floor tile mastic, untested when the estimate was made, contained asbestos. About 1,900 square feet needed abatement instead of simple removal. This was an identified risk; the estimate's pessimistic value for demolition assumed exactly this case. The overrun is a risk that occurred, not a failure of performance.

Electrical overran by $12,200 and is running about ten days behind because the electric utility required the new service entrance on the alley side of the building rather than the street side shown in the design. The change added trenching and about 90 feet of underground conduit, and the utility's crew could not set the new meter until its scheduled date. The transformer, the larger risk in the estimate, proved adequate.

Plumbing overran by $8,500 and finished six days late because the excavation for the grease interceptor struck an old concrete footing from the hardware store's former loading dock. Saw-cutting and removal took three days and the plumbing inspection had to be rescheduled, which took three more. Because plumbing is on one of the two critical paths, interior construction started six days late, and so did everything after it. This is the only gap that moves the finish date, from day 135 to day 141 if nothing is done.

In each case the cause is in the building or in a third party's requirements, not in the arithmetic or the crediting rules. Kerzner (2017) warns that variance analysis often stops at restating a number as a sentence; each explanation above names a physical event that could have been observed on site.

Why the Cost Overruns Are Not a Trend

Three cost overruns in a row can look like a pattern of poor estimating. The causes say otherwise. Each came from a condition hidden in the building or a requirement set by an outside party, and each was either named as a risk in the estimate or fell within its pessimistic range. None came from crews working more slowly or materials costing more than quoted, the kinds of cause that would repeat in the packages still to come. That distinction matters for the forecast in the next unit, because a cost index built from one-time events should not be projected across the remaining work. The PMBOK guide asks that variance analysis determine the cause and degree of each variance and decide whether corrective or preventive action is needed (Project Management Institute, 2017), and the answer here is mostly preventive: test earlier, and check old site records before digging.

Corrective Actions and Owners

Each gap that crossed a threshold receives an action, an owner and a date.

GapActionOwnerByCost
Demolition overrunCharge to contingency against the recorded abatement risk; test all remaining finishes before any future demolitionProject managerMay 29$5,800 from contingency
Electrical overrun and delayApprove change order for the alley service, including remaining conduit; weekly call with the utility's coordinator; escalate if the meter date passes day 100Project manager with electrical contractorJune 5$14,500 from contingency
Plumbing overrunCharge to contingency against the sewer and site risksProject managerMay 29$8,500 from contingency
Six-day critical slipAdd a second interior crew for eight days to recover four days; start walk-in installation in the finished cooler area before the rest of the interior is complete to recover two moreGeneral contractor's superintendentCrew on site June 1$6,800 from contingency

The two schedule actions together are expected to return the finish to day 135. Starting the walk-in installation early changes a finish-to-start dependency into a partial overlap, which is safe because the cooler area's walls and floor are finished first; the superintendent confirmed the sequence. Contingency used so far totals $35,600 of $90,000, with the building systems risks now largely past. Two favorable or small variances, mechanical and design, need no action, but the mechanical underrun was checked to confirm that all rooftop units were set and tested, not credited early. Food Works and all of its figures belong to this course's composite case.

References

Fleming, Q. W., & Koppelman, J. M. (2010). Earned value project management (4th ed.). Project Management Institute.

Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling (12th ed.). Wiley.

Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK guide) (6th ed.). Project Management Institute.

What the BU 442 Unit 7 instructions ask for

BU 442 Unit 7 asks students to analyze the variances found in an earned value calculation and respond to them. Common requirements include thresholds for investigation, a test of each variance, root causes for those that exceed thresholds, corrective actions with owners and dates, and a note on whether favorable variances were checked. Many instructors ask students to set thresholds if the case gives none and to explain their choice. Causes should be traced to events in the work, not restated arithmetic. Actions should be specific enough to carry out, with the cost of each response shown against contingency. A threshold table and an action table, explained in APA 7, are typical, and strong submissions separate one-time events from trends.

How the BU 442 Unit 7 example is put together

The analysis starts with the earned value totals and explains why thresholds are needed. A section states four thresholds set at baseline, and a table tests each package against them, including one that passes the percentage test but not the dollar test. A causes section traces the three cost overruns to specific site conditions and a utility requirement, and shows that only the plumbing delay reaches the finish date. A section argues that the overruns are not a trend. An action table assigns each gap a response, owner, date and cost. A closing paragraph explains how the schedule recovery works, how much contingency has been used and why the favorable mechanical variance was verified.

Where the points sit in the BU 442 Unit 7 rubric

Variance analysis rubrics usually weigh the threshold design, the testing of variances, root cause analysis, the quality of corrective actions and overall judgment, with writing and APA. Threshold design earns full credit when thresholds are stated in advance and combine percentage and dollar tests. Testing is judged on whether every package is checked, including favorable ones. Root cause analysis scores highest when causes are physical events, not restated numbers. Corrective actions earn points when they have owners, dates and costs. The judgment criterion rewards distinguishing one-time events from trends and identifying which gaps affect the finish date, since instructors want to see priorities, not a list.

BU 442 Unit 7 help: mistakes that cost points

Variance analyses commonly lose points by explaining a variance with the variance itself, such as costs were higher than planned. Another frequent problem is investigating every gap with equal effort, burying the ones that matter. Students often ignore favorable variances, which can signal early crediting. Some propose actions without owners or dates. Others miss the difference between schedule gaps in float and gaps on the critical path. Many treat all overruns as trends, which inflates later forecasts. Finally, thresholds invented after seeing the variances look designed to produce a particular answer; stating that they were set at baseline answers that concern before an instructor raises it.

Get a BU 442 Unit 7 example written to your instructions

Forward the Unit 7 instructions with the BU 442 rubric, plus the baseline, the earned value results and any threshold your section fixes. We write a custom example that screens on thresholds, traces each gap to a cause in the work, tests the progress data itself and pairs every finding with an owned action. First custom sample free, back in 24 to 48 hours.

More BU 442 papers and project management samples

BU 442 Unit 7 questions, answered

How do I choose thresholds if the instructions do not give any?

Set them from the case rather than from a habit, and say what they are based on. A gap large enough to matter to the sponsor described in the assignment is one anchor; a gap larger than the estimating error you claimed in an earlier unit is another and reads well because it links the two. State both a money figure and a proportion, since either alone misbehaves at one end.

Should favorable variances be investigated too?

Yes, and skipping them is a common way to lose part of the criterion. An account under budget may mean work was done more cheaply, or it may mean the work has not started and the progress reading is wrong. A favorable gap that turns out to be a measurement problem is worth more in the write-up than a straightforward overrun.

What makes a corrective action strong enough to score?

It has to change something specific and be startable by a named person. Rescheduling an element onto a chain with float, moving a portion of work to a cheaper resource, or releasing contingency against the element it was raised for are all actions. Add what you expect the response to do to the account and by when, so a later unit can check whether it worked.

Where can I find a free BU 442 Unit 7 sample paper?

The BU 442 Unit 7 variance analysis with response is free to read in full on this page, with the threshold test, causes, action table and margin notes. For different variances, email the prompt and a custom analysis follows free, typically within two days.

Should favorable variances be investigated in BU 442 Unit 7?

Large ones should. The sample investigates favorable variances above 10 percent and $5,000, since an underrun can mean work was skipped or credited early. Its mechanical underrun fell below that threshold but was still checked.