BU 345 Unit 3 scope and work breakdown document example

Project Management Herzing University Free custom sample in 24 to 48h

Presented in full, this BU 345 Unit 3 scope and work breakdown document defines seven deliverables for a composite brewery's canning line, attaches an acceptance condition to each, lists what is excluded and why, and decomposes the work into nineteen numbered packages. Herzing BU 345 puts scope ahead of scheduling, and the sample shows project management students how to decompose deliverables rather than activities and when to stop. Acceptance conditions are concrete, such as a line running 40 cans per minute for 30 minutes or 200 cases released from the first run. Five exclusions, from new recipes to a forklift, each carry a reason, and two near-miss items are explained. The outline numbers every element so later units can refer to it, and a dictionary table gives each package an owner, an output and a completion test. A closing section defends where the breakdown stops, citing Haugan and Kerzner.

CourseBU 345 Project Management
UnitUnit 3
Paper typeScope and work breakdown document
LengthAbout 770 words, 5 pages
FormatAPA 7 student paper
SchoolHerzing University
ProgramBS in Project Management
UpdatedSeptember 2026

Free sample paper for BU 345 Unit 3

1

Seven Deliverables, Nineteen Work Packages: A Scope Statement and Work Breakdown Structure for a Composite Brewery's Canning Line, With What Is Excluded

Student Name

Business, Herzing University

BU 345: Project Management

Instructor Name

February 18, 2026

What this page is doingThe title counts the deliverables and packages and promises an exclusions list. Numbers in the title tell the reader the breakdown is complete enough to count, and the exclusions promise protects the sponsor's expectations.
2

Seven Deliverables, Nineteen Work Packages: A Scope Statement and Work Breakdown Structure for a Composite Brewery's Canning Line, With What Is Excluded

Scope Statement

This document defines what Iron Trestle Brewing's canning line project will and will not deliver, following the charter issued in Unit 2. The project will hand over seven deliverables, each with an acceptance condition that the sponsor and project manager will use at closeout to decide whether it was delivered. The deliverables are project management records; a prepared packaging area; an installed canning line with conveyors and inspection tools; approved can labels and a supply contract; a commissioned line that has passed its acceptance test and trial runs; trained operators with written procedures; and a first saleable production run.

The acceptance conditions are as follows. The packaging area is accepted when the electrical inspection is passed and air, CO2 and drainage are connected and tested. The line is accepted when it runs at 40 cans per minute for 30 minutes during the vendor's site acceptance test. Labels are accepted when federal approval is received for all four launch beers. Commissioning is accepted when three trial runs produce double seams within the can maker's specifications on every check. Training is accepted when two operators each run a full shift unassisted. The first saleable run is accepted when at least 200 cases pass quality checks and are released to the warehouse.

Exclusions

The sponsor should not expect the following from this project, each excluded for a stated reason. New beer recipes are excluded because the brewery will can its existing beers, and recipe development belongs to the head brewer's ongoing work. Taproom changes are excluded because they were a separate candidate in the selection record. Negotiation of the grocery distribution agreement is excluded because the owner is handling it directly and the project cannot control its terms. Can purchases beyond the first order are excluded because ongoing packaging materials are an operating cost. A forklift is excluded because the brewery already owns one that can move pallets of empty cans. Writing exclusions down prevents the most common source of disagreement at closeout, a sponsor expecting something the team never agreed to deliver (Project Management Institute, 2017).

Two items came close to inclusion and were left out after discussion with the sponsor. A second conveyor for future bottling was deferred because no bottling plan exists, and a new warehouse racking layout was deferred because the current racks can hold the first year of can inventory.

What this page is doingExclusions are listed with a reason for each. Stating what is out of scope, and why, is what makes a scope statement protect the project later, and many rubrics award separate points for it.
3

Work Breakdown Structure

The breakdown decomposes deliverables, not activities, and stops when a package is small enough for one person to own and estimate. Haugan (2002) describes this as the level at which a work package can be scheduled, costed and assigned to a single responsible party. Each element has a number so that the schedule and budget in later units can refer to it without restating it.

1.0 Project management: 1.1 Plans and baselines; 1.2 Status reporting and change control.

2.0 Packaging area preparation: 2.1 Electrical service upgrade; 2.2 Compressed air and CO2 lines; 2.3 Floor drain and slab repair; 2.4 Electrical permit and inspection.

3.0 Canning equipment: 3.1 Filler and seamer; 3.2 Depalletizer, rinser and conveyors; 3.3 Seam inspection tools.

4.0 Labels and packaging supply: 4.1 Label artwork; 4.2 Federal label approvals; 4.3 Can and lid supply contract.

5.0 Installation and commissioning: 5.1 Set and level equipment; 5.2 Utility connections; 5.3 Site acceptance test; 5.4 Trial runs.

6.0 Training and procedures: 6.1 Operator training; 6.2 Standard operating procedures.

7.0 Launch: 7.1 First saleable production run.

Work Breakdown Structure Dictionary

Each lowest-level package has a dictionary entry giving its owner, what it produces and how completion is recognized. The table below holds the entries. Owners are named by role.

PackageOwnerProducesComplete when
1.1 Plans and baselinesProject managerSchedule, budget, risk registerSponsor signs baselines
1.2 Status and change controlProject managerBiweekly reports, change logFinal report accepted at closeout
2.1 Electrical upgradeElectrical contractorNew panel and circuits to packaging areaCity inspection passed
2.2 Air and CO2 linesElectrical contractor's plumbing subcontractorPiped air and CO2 at line locationPressure test passed
2.3 Drain and slabGeneral contractorFloor drain and sealed slabLandlord walkthrough signed
2.4 Permit and inspectionElectrical contractorIssued permit, final inspectionInspection card signed
3.1 Filler and seamerProject managerDelivered machineReceived undamaged against packing list
3.2 Depal, rinser, conveyorsProject managerDelivered conveyors and rinserReceived against packing list
3.3 Seam toolsHead brewerSeam micrometer and teardown toolsTools calibrated
4.1 Label artworkOwner with designerPrint-ready art for four beersOwner approves proofs
4.2 Label approvalsOwnerFederal label approvalsApproval received for all four
4.3 Can supply contractProject managerSigned supply agreementFirst order confirmed
5.1 Set and levelVendor technicianLine in positionLevel check recorded
5.2 Utility connectionsVendor technician with contractorPower, air, CO2 connectedDry run completed
5.3 Acceptance testVendor technicianTest record30 minutes at 40 cans per minute
5.4 Trial runsHead brewerThree trial batchesAll seam checks in specification
6.1 and 6.2 Training and proceduresProject managerTwo trained operators, written proceduresEach operator runs a shift unassisted

Why the Breakdown Stops Where It Does

Two packages could have been decomposed further and were not. The filler and seamer, package 3.1, involves design, manufacturing and shipping, but all of that is the vendor's work under a fixed-price order, so the brewery's package is the delivered machine. Breaking it down would describe work the brewery does not manage. Operator training and procedures, packages 6.1 and 6.2, share one row in the dictionary because the same person writes the procedures while training the operators, and separating them would create two small packages with one owner and one completion test. Every package in the breakdown is owned by one role, which is the test for stopping. The next unit takes these packages and turns them into a sequence with durations. Iron Trestle Brewing and every figure here are composites created for this course (Kerzner, 2017).

References

Haugan, G. T. (2002). Effective work breakdown structures. Management Concepts.

Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling (12th ed.). Wiley.

Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK guide) (6th ed.). Project Management Institute.

BU 345 Unit 3 instructions, in plain terms

In the scope unit, students write a scope statement and a work breakdown structure for the chartered project. Most versions want the deliverables listed with acceptance criteria, exclusions stated, the work decomposed into a numbered hierarchy and a dictionary entry for each lowest-level package with its owner and completion criteria. Many rubrics ask you to decompose by deliverable rather than by activity and to stop at a level one person can own and estimate. Instructors often check whether exclusions have reasons and whether numbering is consistent. The breakdown can be a chart or an indented list. Expect a few pages of prose plus the outline and dictionary, with PMBOK or other sources cited in APA 7.

How the BU 345 Unit 3 example is put together

The sample's scope statement names seven deliverables and then gives each a specific acceptance condition. An exclusions section lists five items the sponsor should not expect, each with a reason, and mentions two items that nearly made the list. The breakdown appears as an indented, numbered outline of seven deliverables and nineteen packages. A dictionary table follows with an owner, an output and a completion test for every package, and owners are named by role. The final section explains why two packages were not decomposed further: the vendor manages the machine's manufacture, and training and procedures share one owner and one test. It ends by pointing to the schedule unit.

Reading the BU 345 Unit 3 rubric

Herzing's rubric for scope and breakdown work commonly includes the scope statement, the exclusions, the structure of the breakdown and the dictionary. The scope statement earns full points when every deliverable has a verifiable acceptance condition. Exclusions score highest when each has a reason. The breakdown criterion rewards decomposition by deliverable, consistent numbering and packages small enough to estimate and assign. The dictionary is judged by an owner and a completion test for every lowest-level package. Instructors often reward an explanation of where decomposition stops, since that shows judgment rather than habit. Clear formatting and APA citations support presentation, and consistency with the charter from Unit 2 earns further credit.

BU 345 Unit 3 help before you submit

The most common Unit 3 mistake is decomposing into activities, such as call the electrician, instead of deliverables. Another is stopping too early, leaving packages too large to estimate, or going too far and listing tasks that take an hour. Students often skip acceptance conditions, which leaves nothing to check at closeout. Exclusions are frequently missing or given without reasons. Numbering sometimes changes between the outline and the dictionary, which breaks the link to the schedule and budget. Finally, give every package one owner; a package owned by a team or by nobody is a sign it should be split or combined with another.

Get a BU 345 Unit 3 example written to your instructions

Send the Unit 3 instructions and the rubric from your BU 345 classroom, together with the charter you submitted for the same project. We write a custom example that states deliverables and exclusions first, decomposes to a defended level, numbers every element and adds the dictionary entries. First custom sample free, back in 24 to 48 hours.

More BU 345 papers and project management samples

BU 345 Unit 3 questions, answered

How far down should the breakdown go?

Far enough that a package can be estimated and owned by one person, and no further. Sections differ on whether they want a fixed number of levels, so read the instructions first. Where the choice is yours, say in a sentence what rule you applied and apply it evenly, since uneven depth is easier for a marker to see than excessive depth.

Should the outline be a chart or a list?

Either, unless the instructions specify, and an indented numbered list is often safer in a word processor. A chart drawn in a graphics tool tends to arrive unreadable at the margins, or as an image a marker cannot search. Whichever form you use, keep the numbering visible, because that is what the later units will point at.

Do exclusions need a reason?

A short one helps. Saying that training materials sit outside the project because another team owns them tells a sponsor where the work went, while an unexplained exclusion reads as something the writer forgot to plan for. Two or three exclusions with a clause of reasoning each usually earn more than a longer bare list.

Where can I find a free BU 345 Unit 3 sample paper?

Everything in the BU 345 Unit 3 document, from the scope statement to the dictionary, is available free above. To get a breakdown built for your own project, share your charter and the unit prompt, and a free custom scope document will be drafted, typically within about two days.

How far down should the BU 345 Unit 3 breakdown go?

Until each package can be owned, estimated and scheduled by one person or role. The sample stops at nineteen packages and explains why two were not split further. Going deeper usually produces tasks that belong in the schedule rather than the breakdown.